General Water Maintenance and Replacement, Adopted FY 2024 – FY 2029 Capital Improvement Program
The General Water Maintenance and Replacement Program provides for major component replacement of the water distribution system. Major maintenance and replacement of system mains and facilities will be phased and prioritized based on pipe age, material, and localized General Fund projects, thus reducing the adverse impacts caused by frequent outages and the cost premiums experienced from system failure repairs. Increased frequency in water main breaks, funding, and re-prioritization of nearby General Fund projects may cause the replacement order to change as needed.
Contact: publicworks@herndon-va.gov or 703-435-6853
Estimated Dates
|
Project |
Design Begin/End |
Construction Begin/End |
|
Dranesville Road (Park Ave to Fillmore St) |
Summer 2023/Spring 2024 |
Fall 2024/Winter 2024 Project has been completed |
| Folly Lick Sanitary Sewer and Stormwater Improvement Project | Winter 2024 - Early Summer 2025 | |
|
Lisa Court & Crestview Drive (Herndon Parkway to Town Boundary) |
|
Summer 2025/Winter 2026 |
|
Wilshire Drive (Alabama Dr to Magnolia Ln) |
|
FY26 |